55B Oakwood Road Albanvale Construction Update – Sep2018
05/09 2018
Author: FCG Admin
Tags:

Unit 1-7 : Ground Floor & First Floor frames completed. Roofing work ongoing

Unit 8-10: Framing work to be started

Unit 11-14: Framing work completed including roofs. Preparing cladding

Unit 15-17: Group floor frames completed. First floor frame works to commence

Unit 18-22: Group floor frames completed. First floor frames on-going

Unit 23-29: Framing work completed including roofs. Windows installed. Preparing for external cladding

Unit 30-32: External cladding started. Framing work completed including roofs

Unit 33-36: Framing work completed including roofs, Preparing for external cladding

Unit 37-39: Ready for external cladding. Framing work completed including roofs

 

Oakwood Road construction work are expected to be completed early 2019 with registration of plan of subdivision anticipated in early 2019 and settlement to be completed shortly thereafter.