Road boxed and capping material placed.
Proof roll with Council has been successfully carried out, with a few soft spots located and rectified. Road crossing conduits being installed. Class 3 CR and Kerb & Channel to start next week.

Summary Of Works Completed

Earthworks  90 %

Roadworks 35 %

Drainage  98 %

MW Drainage  98 %

Watermain  98 %

Sewer  98 %

Gas  100 %

Adjusted Anticipated Civil Work Completion Date : 30th April 2021